Mabini St.Tarlac, Philippines
Phone(045) 606-1834
✓ Power sources connected to the distribution system or electrical system of the End-Users, that could be aggregated to meet a demand.
✓ Distributed Energy Resources refer to a variety of intermediate-scale power generation facilities that supplies electricity to a consumer/End-User, often installed within or close to where the electricity is used. These could also be aggregated/collected to meet or aid a specific electrical demand.
*NOTE: The DER Program is not applicable to the following:
✓ The DER Program was initiated by the Energy Regulatory Commission (ERC) through Resolution No. 11, Series of 2022. This aims to encourage the development and utilization of DER, promote energy quality, reliability, security, affordability, and sustainability to align with the objectives of the Electric Power Industry Reform Act of 2001 (EPIRA), RE Law, and other relevant laws, rules, and regulations.
✓ DERs that will utilize renewable energies for the End-User’s total consumption and export energy greater than 100 kW to 1 MW.
*NOTE: The capacity limit for facilities that will use Solar Photovoltaic (PV) shall be more than 100 kWp to 1 MWp.
OR
✓ DERs that will only supply for the End-User’s consumption regardless of the generation technology and capacity.
*NOTE: The DER owner and End-User should not be the same entity
✓ Only DERs that utilize renewable energies shall be allowed to export to the distribution system of the Distribution Utility (DU).
✓ For DERs that will utilize renewable energy, the nameplate capacity should be more than 100 kW and should not exceed 1 MW.
*NOTE: The maximum capacity to export shall not exceed 30% of the nameplate capacity.
✓ DERs that will only supply for the End-User’s consumption shall have no capacity limitations.
✓ Letter of Intent
✓ DER Application Form
✓ Electrical Plan
✓ Electrical Permit
✓ Detailed Planning Data
✓ Valid IDs of DER owner and End-User
✓ Technical Specifications of RE Facility
✓ Certificates of RE Facility
✓ SEC Registration
✓ Secretary’s Certificate
✓ Valid IDs of Corporate Secretary and Authorized Representative
✓ Application Form (ERC COC Form 1)
✓ Distribution Utility (DU) Certification
✓ Permit to Operate (PTO) (if applicable)
✓ Renewable DER Supply Agreement
✓ Management and/or Lease Contract (if applicable)
✓ Company Profile (ERC COC Form 2)
✓ Environmental Compliance Certificate (ECC) (if applicable)
✓ Upon submission of the complete Administrative Requirements to the DU (TEI), the necessary technical processes for the issuance of the DU Certification
will be conducted, facilitated, and witnessed by the DU.
✓ Distribution Impact Study
✓ Distribution Assessment Study (if applicable)
✓ DER Facility Testing and Commissioning
✓ Power Quality Test
✓ Upon receipt of the DU Certification from TEI, the applicant may proceed with the submission and processing of their DER Program application to the ERC.
✓ To learn more about the DER Program, you may visit us at our Main Office (J. Luna corner F. Tañedo Streets, Brgy. Poblacion, Tarlac City), message us through
our Facebook page (@tei.ph), or contact us at (045) 606-1834.
TEI HOSTING CAPACITY FOR DISTRIBUTED ENERGY RESOURCES (DER)
As of June 30, 2024
Per Feeder Hosting Capacity | |
Feeder | Maximum Hosting Capacity (kW) |
LIPIEWP | 2,000 |
LIPLINE | 4,000 |
LIPSSMP | 3,000 |
LIPIWSPC | 2,000 |
LIPSNMGL | 2,000 |
LIPHACIENDA | 2,500 |
SANRAFARMENIA | with two (2) connected embedded generating plants with capacity of 7.1MW and 2MW, respectively |
SANRAFSMBINAUGANAN | 4,000 |
SANRAFNORTH | 1,600 |
SANRAFNORHILLS | 2,000 |
SANRAFSOUTH | 3,000 |
MALGLOBE | 5,500 |
MALAMU | 5,500 |
PANGHIWAY | 2,400 |
PANGSCRUZ | with one (1) connected embedded generating plant with capacity of 5.5MW |
PANGNASI | Loads were transferred too San Vicente FDR1 |
PANGSANVIC | Loads were transferred to San Vicente FDR2 |
PANGPOB | 2,200 |
TPCFDR 1 | 5,000 |
TPCFDR 2 | Loads for TPCFDR2 are connected to San Vicente FDR3 |
San Vicente FDR1 | 2,800 |
San Vicente FDR2 | 5,000 |
San Vicente FDR3 | 5,000 |
Per Substation Hosting Capacity | |
Substation | Maximum Hosting Capacity (kW) |
LIP Substation | 15,500 |
San Rafael Substation | 10,600 |
Maliwalo Substation | 5,500 |
Panganiban Substation | 10,100 |
TPC Substation | 5,000 |
San Vicente Substation | 12,800 |